Same Process, Different Names: Decoding the Terminology
Let’s clarify what these different terms mean and how they relate to each other:
Daywork
The Common Challenges - Regardless of What You Call It
The term “daywork” is widely used in the UK, Australia, and many Commonwealth countries. According to RICS (Royal Institution of Chartered Surveyors), daywork is:
“The method of valuing work on the basis of the time spent by the contractor’s team, the materials used and the plant employed.“
Daywork is typically used for:
- Variations to contract work
- Work where scope is not fully defined
- Unforeseen conditions requiring additional effort
- Activities that can’t be easily measured or quantified beforehand
Time and Materials (T&M)
Time and Materials, or T&M, is commonly used in North America and describes:
A contract where the client agrees to pay the contractor based on:
- The time spent by workers at agreed hourly rates
- The cost of materials plus a markup
- Equipment usage at predetermined rates
T&M contracts are structurally identical to daywork arrangements but use different terminology.
Cost Plus
Cost Plus refers to:
A contract where the client pays for:
- All direct costs incurred (labor, materials, equipment)
- Plus an agreed percentage or fixed fee to cover overhead and profit
Cost Plus arrangements follow the same core principle as daywork, and are often used on those projects under design development, that carry high risk, and/or are highly intricate. Often a subcontractor will use all-inclusive rates for its work, and the builder will add a percentage markup to these costs and pass onto its client. In some instances a subcontractor may also be asked to claim its actual costs plus a percentage mark-up instead of all-inclusive rates.
Do-and-Charge
Do-and-Charge is a more colloquial term that describes:
Work performed with billing based on:
- Actual hours worked
- Materials consumed
- Equipment utilised
- With appropriate markups applied afterward
This term is often used informally by contractors for small variations, for additional work outside the main contract scope, or on small scale projects for the sake of simplicity.
Hourly Work / Rates-Based Billing
Some contractors refer to this type of work as hourly work or rates-based billing, where:
Compensation is calculated using:
- Pre-agreed hourly rates for different labor categories
- Equipment rates per hour/day
- Actual cost of materials plus markup
Despite the terminology differences, contractors face the same challenges with all these work arrangements:
- Documentation Burden: Capturing detailed records of time, materials, and equipment
- Delayed Approvals: Getting client sign-off on completed work
- Inefficient Reporting: Compiling information for billing purposes
- Verification Issues: Proving work was completed as claimed
- Communication Gaps: Ensuring all parties understand what work was done and why
- Administrative Overhead: Managing paperwork and forms
- Compliance Concerns: Meeting contractual and regulatory requirements